1600 Smallman

  • Begin installation of retail storefronts on Smallman
  • Continue detailing and grouting the garage

Produce Terminal

  • Install utilities at 21st Street (21st STREET ROAD IS CLOSED BETWEEN RAILROAD AND SMALLMAN FOR 2-4 WEEKS)
  • Continue roof replacement
  • Continue installation of storefront glass
  • Continue clerestory window installation
  • Demolish Auction House interior