1600 Smallman

2/28/2020: Comcast will be working on the 1600 Smallman project utilities along 17th Street.  This may cause a partial lane blockage.

  • Storefront glass continues to be installed along Smallman Street
  • Masonry infill continues along Spruce Way at loading docks

Produce Terminal

The utility work on 21st Street has been completed and the road is opened back up!

  • Install railings on Phase 3 and Phase 4
  • Start concrete ramps and stairs at 21st Street
  • Continue demolition of the Auction House interior