Governor Wolf has reinstated construction work and  our General Contractor and subs have returned to the site with new COVID-19 safety protocols in place.

Produce Terminal

  • Continue underground plumbing in Phase 4
  • Demo and install new windows in two-story Auction House
  • Continue ramps/curbs in Phase 4
  • Continue sprinkler installation
  • Remove ballast from Auction House roof
  • Continue installing lower clerestory frames and glass in Phase 3
  • Continue installation of storefront frames in Phase 3
  • Continue installing and repairing historic wood doors on Spruce Way
  • Start painting Smallman canopy, handrails and bollards
  • Continue installing street lights at Smallman
  • Complete backfill of curbs

1600 Smallman

  • 17th Street window framing is installed, and the glazing will be installed on Sunday May 10
  • Elevator CMU shaft construction has resumed
  • Stair way walls and treads being poured
  • Mulberry Way  concrete sill restoration and window installation has resumed
  • Installation of electrical room and electrical equipment is ongoing
  • Backfill of precast garage will be starting