Anticipated activities next week include:
The Terminal
- Complete Kebony wood benches in Phase 3
- Complete painting of (guardrails, bollards, etc. in Phase 3 along Smallman
- Complete painting historic wood doors in Phase 3
- Install asphalt wearing course in Phases 1 and 2, and continue with asphalt prepwork in Phase 3
- Continue Smallman low roof in Phase 1 and complete Phase 3 canopy roof
- Continue install of Smallman above canopy lights in all phases
- Install Spruceway light poles in all phases
- Pour back the traffic gate islands
- Continue landscaping

1600 Smallman
- Install warehouse freight elevator
- Complete warehouse Stair #2 CMU shaft
- Start up west rooftop air handling unit
- 1st floor warehouse metal stud framing is ongoing
- Demo of Smallman Street sidewalk and dock is ongoing
- Begin delivery of tongue & groove wood plank
- Precast Garage – begin concrete washes (start at 5th floor and work down)
- Precast Garage – electrical, fire protection is ongoing
- Precast Garage – begin installation of passenger elevator
Smallman Street
- The north side of Smallman Street will be paved towards the end of next week
- Contract 1 (sidewalks from 17th through 20th except Iron Born Pizza) should be finishing by the end of June
- Contract 2 (the rest of the sidewalks, plaza construction, street lighting, paving) should be starting in July and ending by November
- The traffic signal at 15th and Smallman will likely be installed in the Spring, finishing by the end of April, due to the lead time for signal poles