Smallman Street is being renovated with the efforts of multiple parties.

McCaffery will be refurbishing the Produce Terminal Building to transform it into new stores, restaurants and offices. McCaffery will perform work on behalf of the City and State to improve public realm elements including the sidewalks, ADA ramps, stairs, street lights, and curb elements on the north side of Smallman Street.

McCaffery will also be doing construction concurrently on the 1600 Smallman building to convert it into ground level retail with offices above and create an adjacent new parking structure, including construction of the new ADA ramps, sidewalks, stairs and curbs associated with this block (16th -17th Street).

Produce Terminal Schedule:

  • Commence Construction: March 2019
  • Substantial Completion- 16th-17th Street: December 2019
  • Substantial Completion- 17th to 18th Street: December 24, 2019
  • Substantial Completion- 18th-20th Streets: January 25, 2020
  • Substantial Completion- 20th to 21st Streets: August 2, 2020

1600 Smallman Schedule:

  • Commence Construction: March 2019
  • Main Building and Below Grade Parking: April 5, 2020
  • Parking Garage and Retail Delivery: June 2, 2020
  • Project Substantial Completion: June 2, 2020

The current fence line will be pushed closer to the Produce Terminal once PWSA completes their work and two lanes of traffic will be maintained on Smallman during the construction.

Please direct questions to Pamela Austin at paustin@mccafferyinc.com

DOMI is responsible for the roadway itself, crosswalks, signage, and the sidewalks, curbs and plazas on the south side of the street between 17th and 21st.

DOMI Schedule:

Final Design*: February to May 2019

Advertise: June/July 2019

Award Contracts: August 2019

Construct: September to December 2019

*Monthly meetings are ongoing first Wednesday of the month at Primanti’s at 3:00 PM.

Please direct questions to domi.smallman@pittsburghpa.gov